St. Thomas Aquinas Catholic Church & Newman Center

Lincoln, Nebraska
?

H&S Plumbing and Heating provided all the mechanical construction on this new 60,000 square foot facility that includes a student center, parish social hall, rectory, multiple classrooms and adjoining 650 seat church the serves the students of the University of Nebraska-Lincoln.

PROJECT SUMMARY
Mechanical Project Cost

$ 1.65 M

General Contractor

Kiewit Building Group

Architect

UNKNOWN

SYSTEMS INSTALLED
  • Geothermal Well field headers

  • Hydronic Loop piping and Pumps

  • 42 Heat Pumps

  • Energy Recovery Ventilators

  • Plumbing Fixtures and Equipment

  • Sanitary Waste and Vent piping

  • Radiant Floor Heating

  • Building Automation System

PROJECT GALLERY